PennDOT Press Release 2024

October 4, 2024

As part of the PennDOT project, its contractor, Marino Corporation, has provided the two-week schedule below from October 7-18, 2024 for the High Street Safety Improvement Project in West Chester. Please be aware that lane & parking restrictions will be in place daily between Lacey Street & Miner Street.

More information can be found on Marino Corporation’s District 6 news page as well as its project webpage.

Distribution
Initials of Personnel
Daylight Working Times 7:00 am - 4:00 pm

Two Week Schedule

PennDOT
West Chester / High Street SIP
ECMS 115425
October 7-19, 2024

Contractors

  • Marino: Marino Corporation
  • Horizon: Horizon Engineers (Survey)
  • Lenni: Lenni Electric (Traffic Signal)
Firm Item of Work M - 10/7 T - 10/8 W - 10/9 T - 10/10 F - 10/11 S - 10/12 M - 10/14 T - 10/15 W - 10/16 T - 10/17 F - 10/18 S - 10/19
  Barnard Street                        
Marino Sidewalk Prep / Install X                      
Marino Demo & Excavation               X        
Marino Grade & Install Granite Curb                 X X    
Marino Sidewalk Prep                     X  
  University Avenue                        
Marino Sidewalk Prep X                      
Marino Install Concrete Sidewalk     X X                
  E. Nields Street                        
Marino Sidewalk Prep X                      
Marino Install Concrete Sidewalk   X X X                
  Linden Street                        
Marino Grade & Install Granite Curb X X                    
Marino Sidewalk Prep / Install       X X              
  Lacey Street                        
Marino Grade & Install Granite Curb         X              
Marino Sidewalk Prep                     X  
  Magnolia Street                        
Marino Grade & Install Granite Curb         X              
  Linden Street                        
Marino Demo & Excavation                        
Marino Grade & Install Granite Curb                        
  Union Street                        
Marino 15" RCP & Inlet 05 & MH-04             X          
Marino Demo & Excavation               X        
Marino Grade & Install Granite Curb                 X X    
Marino Sidewalk Prep                     X  
  Miscellaneous                        
Marino Asphalt Base Restoration in front of Granite Curb             X       X  
  Traffic Signal Work (University Ave & Sharpless St.)                        
Lenni Sharpless - Sidewalk Restoration X X X X X   X X X X X  
Lenni University - Install Conduit & Foundations X X X X X   X X X X X  
  Utility Work                        
Aqua Water Service Replacement (229 High Street)       X                

Notes:

  • Daily Lane Restrictions will be in place On High Street between Linden Street & Miner Street.
  • Awaiting response on RFI regarding Inlet 11.

Upcoming Activites

  • 10/25 10/27 - Homecoming Weekend

 


October 1, 2024

As part of the PennDOT project, its contractor, Marino Corporation, has provided the two-week schedule below from now through October 12, 2024 for the High Street Safety Improvement Project in West Chester. Please be aware that lane & parking restrictions will be in place daily between Lacey Street & Miner Street.

More information can be found on Marino Corporation’s District 6 news page as well as its project webpage.

Distribution
Initials of Personnel
Daylight Working Times 7:00 am - 4:00 pm

Two Week Schedule

PennDOT
West Chester / High Street SIP
ECMS 115425
September 30 - October 12, 2024

Contractors

  • Marino: Marino Corporation
  • Horizon: Horizon Engineers (Survey)
  • Lenni: Lenni Electric (Traffic Signal)
Firm Item of Work M - 9/30 T - 10/1 W - 10/2 T - 10/3 F - 10/4 S - 10/5 M - 10/7 T - 10/8 W - 10/9 T - 10/10 F - 10/11 S - 10/12
  Lacey Street                        
Marino 15" RCP & Inlet 08 & MH-01 X X             X X    
  Magnolia Street                        
Marino Manhole Rebuild X                      
Marino Grade & Install Granite Curb                   X X  
  Miscellaneous                        
Marino Inlet 11   X X                  
  Linden Street                        
Marino Demo & Excavation     X X                
Marino Grade & Install Granite Curb             X          
  University Avenue                        
Marino Demo & Excavation       X                
Marino Grade & Install Granite Curb       X X              
  Barnard Street                        
Marino Grade & Install Granite Curb         X              
  E. Nields Street                        
Marino Grade & Install Granite Curb             X X        
  Traffic Signal Work (University Ave & Sharpless St.)                        
Lenni Sharpless - Install Conduit & Foundations X X X                  
Lenni University - Install Conduit & Foundations       X X   X X X X X  

Notes:

  • Daily Lane Restrictions will be in place On High Street between Linden Street & Miner Street.

Upcoming Activites

  • Saturday 10/5 - "Experience West Chester University" - WCU Event

 


September 27, 2024

As part of the PennDOT project, its contractor, Marino Corporation, will be implementing the following parking restrictions for 9/30 - 10/4:

  • Linden NE Corner, 2 spaces
  • Lacey NE Corner, 2 spaces
  • Nields SE corner, 2 spaces

Marino will remove parking restrictions as work is completed.

More information can be found on Marino Corporation’s District 6 news page as well as its project webpage.

 


September 13, 2024

As part of the PennDOT project, its contractor, Marino Corporation, has provided the two-week schedule below for the High Street Safety Improvement Project in West Chester. Both lane and parking restrictions will be in place daily between University Avenue and Miner Street.

More information can be found on Marino Corporation’s District 6 news page as well as its project webpage.

Distribution
Initials of Personnel
Daylight Working Times 7:00 am - 4:00 pm

Two Week Schedule

PennDOT
West Chester / High Street SIP
ECMS 115425
September 16-28, 2024

Contractors

  • Marino: Marino Corporation
  • Horizon: Horizon Engineers (Survey)
  • Lenni: Lenni Electric (Traffic Signal)
Firm Item of Work M - 9/16 T - 9/17 W - 9/18 T - 9/19 F - 9/20 S - 9/21 M - 9/23 T - 9/24 W - 9/25 T - 9/26 F - 9/27 S - 9/28
  Lacey Street                        
Marino 15" RCP & Inlet 08 & MH-01 X               X X    
Marino Granite Curb Installation                        
  E. Nields Street                        
Marino 15" RCP & Inlet 09   X                    
Marino Granite Curb Installation               X X      
  Magnolia Street                        
Marino 15" RCP & Inlet 07 & MH-02     X                  
Marino Granite Curb Installation
                  X X  
  Union Street                        
Marino Stump Removal       X                
Marino 15" RCP & Inlet 07 & MH-02       X X              
  Barnard Street                        
Marino 15" RCP & Inlet 07 & MH-02             X          
  Utility Work
                       
 Aqua Water Service Replacement (400-500 Blk of High St.)
  X X X X   X X X X X  
  Traffic Signal Work
(University Ave & Sharpless St.)
                       
Lenni Layout & PA One Call Mark-out X X X X X              

Notes:

  • Daily Lane Restrictions will be in place between University Ave & Miner Street.

Upcoming Activites

 


September 10, 2024

As part of the PennDOT project, its contractor, Marino Corporation, shares the following parking restrictions for September 12 and September 13:

  • Nields St. SE corner 1 space / NE corner 1 space

Marino Corporation will remove parking restrictions as they complete work in areas.

More information can be found on Marino Corporation’s District 6 news page as well as its project webpage.

 


September 6, 2024

As part of the PennDOT project, its contractor, Marino Corporation, shares the following parking restrictions for September 9 and 10:

  • Nields St. SE corner 1 space
  • Lacey St. NE corner 2 spaces
  • Magnolia St. NE corner 2 spaces on High / 2 spaces on Magnolia

Marino Corporation will remove parking restrictions as they complete work in areas.

More information can be found on Marino Corporation’s District 6 news page as well as its project webpage.

 


September 6, 2024

As part of the PennDOT project, its contractor, Marino Corporation, has provided the two-week schedule below for the High Street Safety Improvement Project in West Chester. Please know that Marino Corporation will implement daily lane restrictions between University Avenue & Miner Street.

More information can be found on Marino Corporation’s District 6 news page as well as its project webpage.

Distribution
Initials of Personnel
Daylight Working Times 7:00 am - 4:00 pm

Two Week Schedule

PennDOT
West Chester / High Street SIP
ECMS 115425
September 9-21, 2024

Contractors

  • Marino: Marino Corporation
  • Horizon: Horizon Engineers (Survey)
  • KB: Knight Brothers (Tree Rem)
  • Chesco: Chesco Sawcutting
Item of Work M - 9/9 T - 9/10 W - 9/11 T - 9/12 F - 9/13 S - 9/14 M - 9/16 T - 9/17 W - 9/18 T - 9/19 F - 9/20 S - 9/21
Entire Project                        
Pipe & Precast Inlet Delivery X                      
Granite Curb Delivery   X X X X              
E. Nields Street                        
Demo SE Corner X                      
15" RCP & Inlet 09         X              
Granite Curb Installation                     X  
Lacey Street                        
Demo NE Corner X X                    
15" RCP & Inlet 08 & MH-01             X          
Magnolia Street                        
Demo NE Corner   X X                  
15" RCP & Inlet 07 & MH-02               X        
Union Street                        
Demo NE Corner     X X                
15" RCP & Inlet 07 & MH-02                 X      
Barnard Street                        
Demo NE Corner       X                
15" RCP & Inlet 07 & MH-02                   X    
Traffic Signal Work
(University Ave & Sharpless St.)
                       
Install Conduit and Signal Foundations             X X X X X  

Notes:

  • Daily Lane Restrictions will be in place between University Ave & Miner Street.

Upcoming Activites

 


September 5, 2024

On behalf of PennDOT's High Street project, Marino Corporation has posted the following traffic restrictions for the week of September 9, 2024:

  • Nields St. to Barnard St. one lane road (flagging) / shifts from 9 am to 3 pm

More information can be found on Marino Corporation’s District 6 news page as well as its project webpage.

 


September 4, 2024

On behalf of PennDOT's High Street project, Marino Corporation has posted the following parking restrictions to prepare for saw cutting on Friday, September 6:

  • University Ave. SW corner 1 spot / NW corner 1 spot
  • Nield St. to University Ave Southbound No Parking all spots
  • Linden St. NW corner 1 spot
  • South of Linden St. Southbound 3 spots

Marino Corporation will clear parking restrictions as they complete areas. More information can be found on Marino Corporation’s District 6 news page as well as its project webpage.

 


September 4, 2024

As part of the PennDOT project, its contractor, Marino Corporation, has provided the two-week schedule below for the High Street Safety Improvement Project in West Chester, which commenced on September 3. More information can be found on Marino Corporation’s District 6 news page as well as its project webpage.

Distribution
Initials of Personnel
Daylight Working Times 7:00 am - 4:00 pm

Two Week Schedule

PennDOT
West Chester / High Street SIP
ECMS 115425
September 2-14, 2024

Contractors

  • Marino: Marino Corporation
  • Horizon: Horizon Engineers (Survey)
  • KB: Knight Brothers (Tree Rem)
  • Chesco: Chesco Sawcutting
Item of Work M - 9/2 T - 9/3 W - 9/4 T - 9/5 F - 9/6 S - 9/7 M - 9/9 T - 9/10 W - 9/11 T - 9/12 F - 9/13 S - 9/14
Entire Project L                      
Tree Removal (229 S. High Street) A X X                  
Tree Trimming B X X                  
Survey & Layout O   X X X              
Sawcut Pavement R     X X              
Pipe & Precast Inlet Delivery             X          
Granite Curb Delivery               X X X X  
E. Nields Street D                      
Demo SE Corner A           X          
15" RCP & Inlet 09 Y           X X        
Lacey Street                        
Demo NE Corner               X        
15" RCP & Inlet 08 & MH-01                 X X    
Magnolia Street                        
Demo NE Corner                 X      
15" RCP & Inlet 07 & MH-02                   X X  

Upcoming Activities

  • Demo & Drainage, NE Corner of Union St.
  • Demo & Drainage, NE Corner of Barnard St.

 


August, 30, 2024
Dear WCU Community,

As the Chester County region has grown, so has increased traffic on local roadways and byways. The era of growth in our region prompts a heightened focus on making the entire community safer for pedestrians and motorists.

West Chester University continues to advocate for the safety of all students, faculty, staff, and visitors to its campus. Most recently, the University improved pedestrian safety at West Rosedale Avenue and South Church Street by adding a new traffic signal, crossing lights and signage, as well as a designated crosswalk.

Of equal concern is the safety of those both driving on High Street and crossing it as pedestrians, including the many members of our University community. Over the years, the University has been in regular communication with West Chester Borough, PennDOT, and Pennsylvania officials regarding safety along High Street. Our advocacy and PennDOT’s recognition of this issue has resulted in the imminent inception of a High Street Pedestrian Improvement Project. This project will improve pedestrian safety along the High Street corridor by implementing safety enhancements aimed at reducing the occurrences of crashes involving vehicles and pedestrians. Construction will begin this fall from Miner Street to Rosedale Avenue.

As part of the PennDOT project, its contractor, Marino Corporation, will conduct tree trimming /removal operations on Tuesday, September 3, and Wednesday, September 4. For this work, Marino Corporation will need to restrict parking from 9 a.m. to 3 p.m. in the following areas: southbound High Street from Sharpless Street to Nields Street North and southbound High Street from Union Street to Bernard Street northbound of High Street from Bernard Street to Miner Street. Parking restrictions will be removed as Marino Corporation moves through.

Of particular interest to the University community are the upcoming plans for the High Street intersections with Rosedale Avenue, plus Linden, University, Nields, and Sharpless streets. Among the improvements are:

  • placement of additional traffic signals at University Avenue and Sharpless Street;
  • installation of a left-turn lane on northbound High Street at Sharpless Street;
  • installation of a left-turn lane on southbound High Street at Nields Street;
  • improvements to signage and intersection lighting;
  • improvements for public transit riders that include bus shelters and
  • curb extensions and ADA ramps at several intersections to reduce the time required for pedestrians to cross.

Work is being coordinated with the University to reduce the impact on traffic and pedestrians, especially during WCU’s annual and special events including Homecoming, commencements, etc. During construction, one lane of traffic along High Street will be maintained and shifted as necessary so that restrictions to traffic flow are minimized.

The University participates in regular progress meetings with the contractor, the borough and PennDOT. Campus updates will be issued as needed to inform all constituents regarding traffic pattern shifts, pedestrian crossing changes, project timing, and other factors that may impact pedestrians and motorists navigating through and around our campus.

PennDOT expects the entire project to be completed in January 2026.

Please check the WCU homepage and the Ram Report for important updates to the High Street Pedestrian Improvement Project.

Learn more about the High Street Corridor Study, from which these improvements were developed.

Please see the attached media release from PennDot

Sincerely,

Zebulun R. Davenport, Ed.D.
Vice President for University Advancement and External Affairs

WCU West Chester University logo

Todd E. Murphy
Vice President for Finance and Administration

WCU West Chester University logo

 


PennDOT Updates

Pennsylvania Department of Transportation logo

FOR IMMEDIATE RELEASE

August 29, 2024

MEDIA CONTACT: Krys Johnson, krysjohnso@pa.gov

PennDOT to Begin Business U.S. 322 (High Street) Safety Improvement Project in West Chester Borough

King of Prussia, PA – The Pennsylvania Department of Transportation (PennDOT) announced today that construction is scheduled to begin on Tuesday, September 3, for a project to improve safety at the intersections along the Business U.S. 322 (High Street) corridor in West Chester Borough and West Goshen Township, Chester County.

Under this contract, PennDOT's contractor will install new traffic signals at University Avenue and Sharpless Street and provide signal support and related equipment. The project will consist of the installation of retroreflective backplates on existing signals, modern LED luminaries, pedestrian countdown timers at signalized intersections, curb extensions, high-visibility crosswalks, drainage improvements, and comprehensive full-depth pavement restoration, culminating in a complete roadway resurfacing.

This project includes the intersections of Rosedale Avenue, Linden Street, University Avenue, Nields Street, Sharpless Street, Lacey Street, Route 52 (Price Street), Magnolia Street, Dean Street, Union Street, Barnard Street, and Route 842 (Miner Street).

This project aims to improve the efficiency of intersections for the traveling public via vehicular and pedestrian means and to reduce the occurrence of crashes involving vehicles, bicycles, and pedestrians.

Beginning Tuesday, September 3, through Friday, September 6, from 9:00 AM to 3:00 PM, periodic lane closures are scheduled on Business U.S. 322 (High Street) between Rosedale Avenue and Route 842 (Miner Street) for tree removal operations.

Motorists are advised to allow extra time when traveling near and through the work area because backups and delays will occur. All scheduled activities are weather dependent.

Marino Corporation of Skippack, Pennsylvania, is the general contractor on the $2,619,998 project which is financed with 100 percent federal funds. Physical construction on the project is expected to finish in winter 2026.

Motorists can check conditions on major roadways by visiting www.511PA.com. 511PA, which is free and available 24 hours a day, provides traffic delay warnings, weather forecasts, traffic speed information, and access to more than 1,000 traffic cameras. 511PA is also available through a smartphone application for iPhone and Android devices, by calling 5-1-1, or by following regional X alerts.

For a complete list of construction projects impacting state-owned highways in Bucks, Chester, Delaware, Montgomery, and Philadelphia counties, visit the District 6 Traffic Bulletin.

Subscribe to PennDOT news and traffic alerts in Bucks, Chester, Delaware, Montgomery, and Philadelphia counties at www.penndot.pa.gov/District6.

Information about infrastructure in District 6, including completed work and significant projects, is available at www.penndot.pa.gov/D6Results. Find PennDOT's planned and active construction projects at www.projects.penndot.gov.

Follow PennDOT on X and like the department on Facebook and Instagram.